LBNE Internal CDR, Cost and Schedule Review

WBS 1.5 Liquid Argon Far Detector

The LBNE Project Manager has called a series of reviews, one for each of the Level 2 sub-projects (neutrino beam, near detector, water Cherenkov far detector, liquid Argon far detector, conventional facilities). The purpose of these reviews is to examine the status of the Conceptual Design and the corresponding cost and schedule estimates for each of the subprojects of the Long-Baseline Neutrino Experiment (LBNE), to identify areas of weakness, and to recommend actions necessary to bring these elements to the level required for a successful DOE CD-1 review.

This review is taking place at Fermilab from 1-3 Nov, 2010. The review committee consists of:

  1. Cryostat, Cryogenics: Johan Bremer (CERN), Flavio Cavanna (L'Aquila), Tom Peterson (FNAL)
  2. TPC (incl. FE electronics): Peter Limon (consultant), Francesco Pietropaolo (Padova), Helmuth Spieler (LBNL)
  3. DAQ, Photon Detector, Veto System: André Rubbia (ETH), Dan Green (FNAL), (Flavio Cavanna)*

* Flavio Cavanna will join subcommittee 3 for the Photon Detector and Veto System presentations.

Agenda

Monday 1 November 2010
Start Title Presenter; Reviewers Room
8:00-9:00 Committee Executive Session 159E
Plenary Session Bldg 327 meeting room
Video: ESnet Ad-Hoc 82LBNE
Ph only: 510-883-7860 (82LBNE#)
9:00-9:05 Introductions J.Strait
9:05-9:35 Science Goals and Experimental Requirements G.Rameika
9:35-10:15 LArTPC Overview B.Baller
10:15-10:30 Break
10:30-11:10 WBS 1.5.2 Cryostat and Cryogenics R.Rucinski
11:10-11:50 WBS 1.5.3 TPC B.Yu/C.Thorn
11:50-12:15 WBS 1.5.4 DAQ J.Urheim
12:15-13:15 Lunch
13:15-13:30 WBS 1.5.6 Photon Detectors B.Baller
13:30-13:50 WBS 1.5.7 Veto System J.Paley
13:50-14:20 WBS 1.5.5 Installation and Commissioning J.Howell
14:20-14:50 R&D/Prototyping Plans B.Baller
14:50-15:15 Cost and Schedule Overview B.Baller
Breakout Sessions
15:15-17:00 Breakout Session:
Cryostat and Cryogenics
B.Norris et al;
J.Bremer, F.Cavanna,
T.Peterson
Bldg 327
Video: ESnet Ad-Hoc 82LBNE
Ph only: 510-883-7860 (82LBNE#)
15:15-17:00 Breakout Session:
TPC Alternate Design

F.Sergiampietro
B.Yu/C.Thorn;
P.Limon, H.Spieler
F.Pietropaolo
159E
15:15-17:00 Breakout Session:
DAQ
J.Urheim et al;
A.Rubbia, D.Green
159W
17:00-18:00 Executive Session 159E
18:00 Adjourn for the day
Tuesday 2 November 2010
Start Title Presenter; Reviewers Room
8:00-12:00 Breakout Session:
Cryostat and Cryogenics
B.Norris et al;
J.Bremer, F.Cavanna,
T.Peterson
WH7XO Racetrack
Video: ESnet Ad-Hoc 823418
Ph only: 510-883-7860 (823418#)
8:00-12:00 Breakout Session:
TPC Reference Design
Front-end electronics

B.Yu et al;
P.Limon, H.Spieler
F.Pietropaolo
WH8NXO Hornet's Nest
8:00-12:00 Breakout Session:
Installation and Commissioning
J.Howell et al;
A.Rubbia, D.Green
WH2NE Snake Pit
12:00-13:00 Lunch
13:00-16:00 Breakout Session:
Cryostat and Cryogenics
B.Norris et al;
J.Bremer, F.Cavanna,
T.Peterson
WH13XO Fish Tank
Video: ESnet Ad-Hoc 823418
Ph only: 510-883-7860 (823418#)
13:00-16:00 Breakout Session:
Front-end electronics (cont'd)
B.Yu/C.Thorn;
P.Limon, H.Spieler
F.Pietropaolo
WH10NW The West Wing
Video: ESnet Ad-Hoc 823201
Ph only: 510-883-7860 (823201#)
13:00-16:00 Breakout Session:
Photon Detectors, Veto System
B.Baller et al;
A.Rubbia, D.Green,
F.Cavanna
WH3NW (Theory)
16:00-17:30 Committee Executive Session WH One North
17:30-18:00 Questions from the review committee WH One North
18:00 Adjourn for the day
Wednesday 3 November 2010
Start Title Presenter; Reviewers Room
08:30-09:30 Response to questions WH One North
9:30-11:00 Breakout Session:
Cryostat and Cryogenics
B.Norris et al;
J.Bremer, F.Cavanna, T.Peterson
159E
9:30-11:00 Breakout Session:
TPC, including Front-end electronics

B.Yu et al;
P.Limon, H.Spieler
F.Pietropaolo
159W
9:30-11:00 Breakout Session:
DAQ, Photon Detectors, Veto System, Integration, Installation and Commissioning
J.Urheim et al;
A.Rubbia, D.Green
WH One North
11:00-12:00 Committee Executive Session 159E
12:00-13:00 Committee Executive Session/Working Lunch 159E
13:00-16:00 Committee Executive Session/Report Writing 159E
16:00-17:00 Closeout Report Presentation Bldg 327 meeting room
Video: ESnet Ad-Hoc 82LBNE
Ph only: 510-883-7860 (82LBNE#)
17:00 Adjourn

Top of page

Primary Documents

Title Access
Draft Conceptual Design Report, see "CDR Volume 5 - Liquid Argon Detector" "review"+password
LAr WBS Dictionary "review"+password
Requirements and Parameters (LAr detector) "review"+password
LAr20 costs with hyperlinks to the BOE documents "review"+password
WBS 1.5 (LAr) Resource-loaded Schedule "review"+password
DUSEL Interface Requirements (for WCD) "review"+password

Supporting Documents

Title Access
LAr20 Risk Assessment "review"+password
Integrated LAr R&D Plan "review"+password
Final Cryogenics conceptual design report at 800L (ARUP) "review"+password
ARUP 800L Cost Estimate (extract of previous doc) "review"+password
Risk Management (from Draft CDR) open
LBNE Preliminary ODH Assessment "review"+password
Quality Assurance (from Draft CDR) open
Hazard Analysis (from Draft CDR) open
Draft Key Assumptions "review"+password
Key Assumptions: Physics Research Goals of the LBNE Project "review"+password
The Modular LANNDD 20kton Detector Design "review"+password
LBNE Organization Chart "review"+password
Final Cryogenics conceptual design report at 800L "review"+password

Top of page

Last modified: 06/28/2019 |